2.2.2 Flange-Style Flow Meter Installation
Install the ange-style meter between two conventional pipe anges of the same nominal
size as the ow meter. If the process uid is a liquid, make sure the meter is located where
the pipe is always full. This may require locating the meter at a low point in the piping
system. Note: Vortex ow meters are not suitable for two-phase ows (i.e., liquid and gas
mixtures). For horizontal pipelines having a process temperature above 300° F, mount the
meter at a 45° or 90° angle to avoid overheating the electronics enclosure. To adjust the
viewing angle of the enclosure or display/keypad, see page 34 and 35.
Figure 7. Flange-Style Flow Meter Installation
CAUTION
When using toxic or corrosive gases, purge the line with inert gas for a minimum of four hours at
full gas ow before installing the ow meter.
When installing the meter make sure the ange marked with a ow arrow is positioned
upstream of the outlet ange, with the arrow head pointing in the direction of ow. (The
mark is on the ange adjacent to the enclosure mounting neck.) This ensures that the
sensor head is positioned downstream of the vortex shedder bar and is correctly aligned to
the ow. Installing the meter opposite this direction will result in completely inaccurate
ow measurement. To install the meter:
1. Conrm that the installation site meets the required minimum upstream and
downstream pipe diameters. Turn off the ow of process gas, liquid or steam. Verify
that the line is not pressurized.
2. Seat the meter level and square on the mating connections with the ange stamped
with a ow arrow on the upstream side, with the arrow head pointing in the direction
of ow. Position a gasket in place for each side. Make sure both gaskets are smooth
and even with no gasket material extending into the ow prole. Obstructions in the
pipeline will disturb the ow and cause inaccurate measurements.
3. Install bolts in both process connections. Tighten the nuts in the sequence shown in
Figure 5. Check for leaks after tightening the ange bolts.